Dec 2026
Possession
31.8%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 31.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
amit sunil shah

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53000077118
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
31.8% complete
Units sold
0 of 0

Similar projects in Tarabai Park

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.