PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MORYA APARTMENTMahaRERA P53100005998

by YUVRAJ JAYSINGRAO PATIL

C S NO 2516, Sangli Miraj Kupwad (M Corp.), 416416

Apr 2018
Possession
100%
Built
0
Complaints
0
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P53100005998
Status
Ongoing
Stage
Certificate Signed
Possession
April 2018
Construction
100% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drainsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station40%

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of MORYA APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MORYA APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.