SHREE RAJLAXMI MALLMahaRERA P53100025856

by SHREE RAJLAXMI CONSTRUCTIONS AND BUILDERS

921/1A/1 921/2, SANGLI, 415414

Sept 2027
Possession
54.1%
Built
0
Complaints
211
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jul 2024, now proposed Sept 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.

Official RERA facts

Registration
P53100025856
Status
New
Stage
Certificate Signed
Possession
September 2027originally July 2024
Construction
54.1% complete
Units sold
46 of 211

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Landowner

SHANKAR NEWANDRAM BUDHWANI

Possession extension history

  • EXT53100019176Revised to March 2026

    Respected Sir/Madam, In the said project, We Shree Rajlaxmi Constructions and Builder purchased the adjacent land/Plot at north side of said project on 23/09/2022. Then we had completed the procedure of amalgamation of adjacent plot and said project plot from Sangli Miraj Kupwad Municipal Corporation on 01/09/2022. After amalgamation both lands/Plot are considered as one plot. Then We had taken revised building permission for newly amalgamation plot with additional built-up area on 02/03/2023. Hence as construction work and activities are increased, we required an additional time to complete said project. The said project is progressing as per schedule. We estimate that it will take another 2 Years to complete whole work. Due to completion date, we have given before, we are facing difficulty for documentary work required for progress of said project. So, I request you to give extension for above mentioned project. We assure that, we will complete said project in that period absolutely.

  • EA18032620261Revised to September 2027

    Respected Sir/Mam, In the said project, Pursuant to the revised permissions granted by the competent authority, the scope of construction of the project has increased substantially. The addition of slabs, internal walls, and extended finishing works has resulted in an increase in the overall quantum of work. Fortunately, almost all of the RCC work, brickwork, and plasterwork has been completed. Further, as the project is a large-scale commercial development, discussions and coordination with multiple brands for internal shop fit-outs are currently in progress. The said process involves detailed planning and requires additional time for the finalization of internal layouts of individual units and their subsequent execution. Considering the scale and magnitude of the project, comprising 211 units, significant time is required for carrying out and completing various finishing works, including plastering, tiling, plumbing, electrification, and installation of fire-fighting systems. Additionally, adherence to prescribed quality standards and regulatory requirements necessitates further time for proper execution of these works. We confirm that consent from all the allottees has been duly obtained in accordance with the applicable provisions of the Real Estate (Regulation and Development) Act, 2016 and the rules made thereunder. In view of the above facts and circumstances, we require additional time for completion of the project. Accordingly, we request the Hon’ble Authority to grant an extension of 1.5 (one and a half) years for completion of the project under the provisions of the Act. We assure the Authority that all necessary steps and efforts are being undertaken to complete the project within the extended timeline.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains60%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposal20%
Water conservation /Rain water harvesting40%
Open Parkingnot started

Building & registration

RERA registered
Jul 2020
Floors
9
Unit mix
0 res · 211 comm
Plot / CTS / survey no.
921/1A/1 921/2
Planning authority
Sangli Kupwad Miraj Municipal Corporation
Approved layout land
2,533 sq.m
Land for this registration
2,533 sq.m
Recreational open space
400 sq.m
Permissible built-up area
3,840.65 sq.m
Registered office
BAAPJI ARCADE
Plot boundaries
North
Adj S No 932
South
Sangli Miraj Road
East
Adj S No 921 1A 2
West
ROAD
Parking
37 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • ICICI BANK LIMITED — 68775
    IFSC ICIC00MMCBL
    KARAD ROAD VITA

Commencement Certificate documents

  • building permition.pdf
  • na order sangli mall.pdf
  • Rajlaxmi Revised Commencement Certificate.pdf
  • Rajlaxmi Commencement Certificate Renew.pdf

Buyer community

Connect with other buyers and owners of SHREE RAJLAXMI MALL — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching SHREE RAJLAXMI MALL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.