MahaRERA P53100030842Caution

by GHEWAREAWATEASSOCIATES

NEW S NO 182 1B 1 B PLOT NO 3 4 5 AND 6, NEAR AKASHWANI, 416416

Official record
Dec 2026
Possession
18.5%
Built
0
Complaints
17
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 18.5%.

Official RERA facts

Registration
P53100030842
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
18.5% complete
Units sold
8 of 17

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Building & registration

RERA registered
Sept 2021
Floors
9
Unit mix
0 res ยท 17 comm
Plot / CTS / survey no.
NEW S NO 182 1B 1 B PLOT NO 3 4 5 AND 6
Planning authority
Sangli Miraj Kupwad city municipal corporation
Approved layout land
3,933 sq.m
Land for this registration
3,933 sq.m
Recreational open space
0 sq.m
Permissible built-up area
10,734.91 sq.m
Registered office
SHIVGURU
Plot boundaries
North
15 MT ROAD
South
S NO 185 1B 2
East
PLOT NO 7
West
PLOT NO 2
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • RBL Bank Limited โ€” 109861
    IFSC RATN0000043
    GAONBHAG SANGLI

Commencement Certificate documents

  • building permission certificate REVISED.pdf
  • BANDKAM PARWANA.pdf

Buyer community

Connect with other buyers and owners of ATHARVA CITY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ATHARVA CITY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.