SHREE GANESH ALANKAR
S NO 88/ 3 PLOT NO 1, VISHRAMBAG, 416416
- Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P53100034004
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2025originally December 2024
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EXT53100027244Revised to March 2025
ACORDING TO THE SANCTION HAS BEEN COOMPLETED THE PROJECT DT 21.10.2024 RECEIVED OCCUPANCY CERTIFICATE DT 4/2/2025. ALSO ENCLOSED ARCHITECT COMPLETION. UPLOADED OCCUPANCY CERTIFICATE AND FORM 4 CERTIFICATE SO REQUEST FOR GRANT PERMISSION EXTESION PROJECT UPTO 31 03 2025
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2022
- Floors
- 7
- Plot / CTS / survey no.
- S NO 88/ 3 PLOT NO 1
- Planning authority
- Others
- Approved layout land
- 880.25 sq.m
- Land for this registration
- 880.25 sq.m
- Permissible built-up area
- 2,647.15 sq.m
- Registered office
- GANESHVANDAN
- North
- S NO 373
- South
- PLOT NO2
- East
- ROAD
- West
- PLOT NO 3 AND 2
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- DCB BANK LIMITED โ 42650IFSC DCBL0000206SANGLI
Commencement Certificate documents
- PERMISSION LATTER.pdf
Buyer community
Connect with other buyers and owners of SHREE GANESH ALANKAR โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHREE GANESH ALANKAR. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.