infinity tower by samaniMahaRERA P53100034355
1143/b, balaji mill road, 416416
- Behind schedule. Possession is due Dec 2026 but construction is only at 23.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P53100034355
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 23.6% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
AKHIL ANIL SAMANI
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Apr 2022
- Floors
- 16
- Plot / CTS / survey no.
- 1143/b
- Planning authority
- Others
- Approved layout land
- 2,968.7 sq.m
- Land for this registration
- 2,968.7 sq.m
- Permissible built-up area
- 7,069.08 sq.m
- Registered office
- THE SIGNATURE APP
- North
- remaining land ext cts no 1143 B and road
- South
- ROAD
- East
- ext cts no 1521
- West
- ext cts no 1143 c
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- HDFC BANK โ 48681IFSC HDFC0000222640 VENKATESH SENATE KARMAVEER BHAURAO PATIL CHOWK SANGLI
Commencement Certificate documents
- building permission.pdf
Buyer community
Connect with other buyers and owners of infinity tower by samani โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching infinity tower by samani. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.