PropPin
All RERA projects
🏗️
Under construction

Euphoria Pride Building A West Side

MahaRERA P53100047641High risk

by Swastik Vastu Private Limited

78B, North Shivaji Nagar, 416416

Official record
Apr 2026
Possession
81.8%
Built
2
Complaints
55
Units
High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 81.8%.

Official RERA facts

Registration
P53100047641
Status
New
Stage
Certificate Signed
Possession
April 2026originally July 2025
Construction
81.8% complete
Units sold
34 of 55

RERA complaint record2 records

Litigation record2 cases

  • THE MAHARASHTRA REAL ESTATE REGULATORY AUTHORITYCase CC005000000177863/2022
    Complainant want Project Registration be cancelled.
    Status: Ongoing
  • THE MAHARASHTRA REAL ESTATE REGURATORY AUTHORITY MUMBAICase CC005000000177863/2022
    COMPLAINANT SEEKING DIRECTIONS FROM THE MahaRERA TO REVOKE/CANCEL THE PROJECT REGISTRATION GRANTED IN FAVOUR OF THE COMPANY.
    Status: Closed

Possession extension history

  • EXT53100028286Revised to April 2026

    We Swastik Vastu Private Limited has registered Project named as Euphoria Pride Building A West Side having MahaRERA project registration number – P53100047641. Our project faced three complaints, registered against us. One in civil court Sangli and other two in Maharera Authority. Civil suit (suit No. – 446/2022) against the promoter before Hon’ble Sangli Civil Court. Plaint of the said civil suit is rejected on merits. Hon’ble Court has passed their order (Dt. – 03/05/2023) regarding the same. Complaint against the promoter before MahaRERA Authority, Complaint No. – CC005000000198005. Said complaint is dismissed on merits. Hon’ble Authority has passed their order (Dt. 04/05/2023) regarding the same. A complaint (complaint No.- CC005000000177863), before MahaRERA Authority . Said complaint is dismissed on merits on Dt. 11/11/2024. Due to above scenario, getting project loan delayed. Also potential customers are hesitant to do agreement for sale for long time. Project construction is in full swing right now, as AFS with many costomers is done now till 31/03/2025. In such scenario, we are hopeful to complete the project in next one year. Amid slow down in market, please consider our request and grant us project registration extension for approximately 9 Months.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Nov 2022
Floors
8
Unit mix
38 res · 17 comm
Architect
Sambhaji Patil
Plot / CTS / survey no.
78B
Planning authority
SANGLI MIRAJ AND KUPWAD CORPORATION
Approved layout land
4,490.85 sq.m
Land for this registration
4,490.85 sq.m
Permissible built-up area
6,375.65 sq.m
Registered office
Euphoria
Plot boundaries
North
Remaining part out of CTS no 78
South
Road
East
CTS No 79
West
CTS No 77B and 77A
Parking
53 four-wheeler35 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • RAJARAMBAPU SAHAKARI BANK LIMITED — 111287
    IFSC RRBP0000034
    SANGLI,KARMVIR CHOWK,SANGLI416416

Commencement Certificate documents

  • Commencement certificate BANDHAKAM PARVANA.pdf
  • Revised Building Permission Certificate_compressed.pdf

Buyer community

Connect with other buyers and owners of Euphoria Pride Building A West Side — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching Euphoria Pride Building A West Side. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.