SHRI GAYATRIMahaRERA P53100077373
CTS no 5988, SANGLI, 416416
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P53100077373
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 46.4% complete
- Units sold
- 7 of 17
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
ANIKET BALASAHEB BHOSALE
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2024
- Floors
- 6
- Unit mix
- 17 res ยท 0 comm
- Architect
- SACHIN KANOJE
- Plot / CTS / survey no.
- CTS no 5988
- Planning authority
- SANGLI MIRAJ KUPWAD CORPORATION
- Approved layout land
- 594.7 sq.m
- Land for this registration
- 594.7 sq.m
- Permissible built-up area
- 1,349.77 sq.m
- Promoter contact
- ANIKET BALASAHEB BHOSALE
- Registered office
- NA
- North
- CTS NO 5984
- South
- ROAD
- East
- CTS NO 5989
- West
- CTS NO 5987
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- IDBI BANK โ 58883IFSC IBKL0000487VYANKATESH EMBASSY,, OPP. SANGLI ZILLA PARISHAD,, SANGLI, PINCODE - 416416
Commencement Certificate documents
- Building sanction certificate (SG).pdf
Buyer community
Connect with other buyers and owners of SHRI GAYATRI โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHRI GAYATRI. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.