PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Happinest Boisar Phase III

by Mahindra Lifespace Developers limited

Gut no 50 plot no 1, Palghar, 401501

Dec 2018
Possession
81.8%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 81.8%.

Official RERA facts

Registration
P99000000106
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposal80%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station95%
Water Treatment Plantdone

Building & registration

RERA registered
Jul 2017
Floors
5

Buyer community

Connect with other buyers and owners of Happinest Boisar Phase III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Happinest Boisar Phase III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.