Under construction

Haridwar SiddhMahaRERA P99000004713

by Haridwar Corp

45/1 and 2, 47/1 and 146/06, Virar West, 401303

Dec 2026
Possession
87.7%
Built
2
Complaints
99
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P99000004713
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
87.7% complete
Units sold
34 of 99

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains90%
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Aug 2017
Floors
17
Unit mix
88 res ยท 10 comm
Architect
Ajay Wade

Buyer community

Connect with other buyers and owners of Haridwar Siddh โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Haridwar Siddh. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.