PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Swastik Epitome Building 2 Phase III 15 to 21 floors

by MAHAVIR HOMES

185/B/1, 185/B/2, 185/B/3, 185/B/4, 185/B/5 OLD S NO 240,241, Vasai, 401305

High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P99000005964
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally December 2021
Construction
76.8% complete
Units sold
76 of 177

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Internal Roads & Footpaths80%
Internal Roads & Footpaths50%
Internal Roads & Footpaths80%
Water Supply50%
Water Supply80%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsnot started
Storm Water Drains50%
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Landscaping & Tree Planting50%
Landscaping & Tree Planting80%
Street Lightingnot started
Street Lighting80%
Street Lighting50%
Community Buildings50%
Community Buildingsnot started
Community Buildings80%
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Water50%
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposal50%
Solid Waste Management And Disposal80%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvesting50%
Water conservation /Rain water harvesting80%
Energy managemcntnot started
Energy managemcnt80%
Energy managemcnt50%
Fire protection and fire safety requirements80%
Fire protection and fire safety requirements50%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station80%
Electrical meter room, sub-station, receiving station50%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Open Parkingnot started
Open Parkingnot started
Temple80%
Temple50%
Club House80%
Club House50%
Templenot started
Club Housenot started

Building & registration

RERA registered
Aug 2017
Floors
9
Unit mix
177 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Swastik Epitome Building 2 Phase III 15 to 21 floors โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Swastik Epitome Building 2 Phase III 15 to 21 floors. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.