Under construction

Acropolis 1MahaRERA P99000007415

by Bhoomi & Arkade Associates

37-46 part 51-67part 98-121part 124 145 147 368 and others as per title certificate attached, Virar West, 401303

Dec 2021
Possession
89.1%
Built
29
Complaints
0
Units
High risk
  • 29 RERA complaints. 29 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 89.1%.

Official RERA facts

Registration
P99000007415
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
89.1% complete
Units sold
0 of 0

RERA complaint record29 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station86%
Aggregate area of recreational Open Spacedone
Podium with Clubhousedone

Building & registration

RERA registered
Aug 2017
Floors
17

Buyer community

Connect with other buyers and owners of Acropolis 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Acropolis 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.