PropPin
All RERA projects
🏗️
Under construction

SUKHKARTAMahaRERA P99000007883

by SUKHKARTA DEVELOPERS

21/4 21/5, nallasopara west, 401203

Mar 2027
Possession
75.9%
Built
0
Complaints
93
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P99000007883
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally June 2021
Construction
75.9% complete
Units sold
61 of 93

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
6
Unit mix
87 res · 6 comm

Buyer community

Connect with other buyers and owners of SUKHKARTA — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching SUKHKARTA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.