IDEAL AVENUE BUILDING NO 3 TYPE B1D WING BMahaRERA P99000009483

by SHREE SAI SAMARTH BUILDERS AND DEVELOPERS

SURVEY NO 179, 180, 181, UMROLI, 401404

Apr 2027
Possession
38.2%
Built
0
Complaints
37
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 38.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P99000009483
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally December 2022
Construction
38.2% complete
Units sold
15 of 37

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
5
Unit mix
24 res ยท 13 comm
Architect
RENDER POINT

Buyer community

Connect with other buyers and owners of IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching IDEAL AVENUE BUILDING NO 3 TYPE B1D WING B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.