Under construction

CRD Gardenia Apartments 6MahaRERA P99000009989

by Dr Chandrashekhar Raghunath Dound

48/1A/1B, Palghar, 401404

Sept 2022
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Sept 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 81.8%.

Official RERA facts

Registration
P99000009989
Status
Ongoing
Stage
Certificate Signed
Possession
September 2022originally December 2019
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains20%
Landscaping & Tree Planting40%
Street Lighting40%
Community Buildings90%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space90%
Open Parking90%

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of CRD Gardenia Apartments 6 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching CRD Gardenia Apartments 6. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.