Under construction

OM SAI COMPLEXMahaRERA P99000010987

by VARSHA PRAKASH NAIK

SURVEY NO. 109/1,2,3, Betegaon, 401501

Dec 2027
Possession
67.7%
Built
1
Complaints
132
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2022, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000010987
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2022
Construction
67.7% complete
Units sold
55 of 132

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting20%
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
5
Unit mix
40 res ยท 92 comm

Buyer community

Connect with other buyers and owners of OM SAI COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OM SAI COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.