PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

RAJYOG ELANZAA

by RAJYOG INFRA

Plot 3 and 16, CTS 43/P3, 34/3B1, 34/3 B2, Palghar, 401404

Dec 2018
Possession
10.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 10.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2018 per the RERA filing.

Official RERA facts

Registration
P99000011072
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
10.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
3

Buyer community

Connect with other buyers and owners of RAJYOG ELANZAA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAJYOG ELANZAA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.