SHREE RADHEYSHYAM NAGARMahaRERA P99000011878
119,120,121, Kudus (CT), 421312
Dec 2030
Possession
54.5%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~7 yrs. Originally promised Dec 2023, now proposed Dec 2030 per the RERA filing.
Official RERA facts
- Registration
- P99000011878
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2030originally December 2023
- Construction
- 54.5% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains50%
Landscaping & Tree Planting40%
Street Lighting10%
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Space25%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 3
Buyer community
Connect with other buyers and owners of SHREE RADHEYSHYAM NAGAR โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHREE RADHEYSHYAM NAGAR. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.