SIDDHIVINAYAK TOWER

by SIDDHIVINAYAK DEVELOPERS

S.NO.196 H.NO.13/9,4/1,3A,5 TO 8,10,11,12/S.NO 197, H.NO 8,10,S.NO.202,H.NO.4/1,13/2,S.NO.204,H.NO35, Vasai, 401305

Feb 2018
Possession
81.6%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Feb 2018) has passed with construction at 81.6%.

Official RERA facts

Registration
P99000012579
Status
Ongoing
Stage
Certificate Signed
Possession
February 2018
Construction
81.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains50%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
LIFT98%

Building & registration

RERA registered
Sept 2017
Floors
8

Buyer community

Connect with other buyers and owners of SIDDHIVINAYAK TOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SIDDHIVINAYAK TOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.