๐Ÿ—๏ธ
Under construction

Bharat ArcadeMahaRERA P99000013206

by Pankaj Chauhan

72/167, 0, 401303

Mar 2027
Possession
47.3%
Built
4
Complaints
47
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Aug 2019, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 47.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P99000013206
Status
New
Stage
Certificate Signed
Possession
March 2027originally August 2019
Construction
47.3% complete
Units sold
34 of 47

RERA complaint record4 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2017
Floors
14
Unit mix
47 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Bharat Arcade โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Bharat Arcade. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.