PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Vakratund Heights

by Shivanjali Infrastructure

Sr. No. 77/3/2, Palghar East, 401404

Dec 2022
Possession
90.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 90.5%.

Official RERA facts

Registration
P99000020206
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
90.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2019
Floors
7

Buyer community

Connect with other buyers and owners of Vakratund Heights โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vakratund Heights. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.