Under construction

Shiv Shanti ResidencyMahaRERA P99000020975

by Shree Guruji Infra

Survey No-1101 & Survey No-1313, Plot No -4 and 5, tembhode naka, 401404

Oct 2028
Possession
โ€”
Built
0
Complaints
130
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Oct 2024, now proposed Oct 2028 per the RERA filing.

Official RERA facts

Registration
P99000020975
Status
New
Stage
Certificate Signed
Possession
October 2028originally October 2024
Construction
โ€”
Units sold
48 of 130

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting50%
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2019
Floors
5
Unit mix
130 res ยท 0 comm
Architect
GAURESH P NAVALKAR

Buyer community

Connect with other buyers and owners of Shiv Shanti Residency โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shiv Shanti Residency. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.