All RERA projects
๐๏ธ
Under construction
SHIV KRUPAMahaRERA P99000021088
Gut No.184/A, Village Umroli, District Palghar, Gut 184/A , Umroli Village, 401404
Oct 2026
Possession
87.3%
Built
0
Complaints
93
Units
High risk
- Possession delayed ~4 yrs. Originally promised Nov 2022, now proposed Oct 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Official RERA facts
- Registration
- P99000021088
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2026originally November 2022
- Construction
- 87.3% complete
- Units sold
- 63 of 93
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving station80%
Open Parkingnot started
Building & registration
- RERA registered
- May 2019
- Floors
- 9
- Unit mix
- 66 res ยท 27 comm
Buyer community
Connect with other buyers and owners of SHIV KRUPA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHIV KRUPA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.