Under construction

Star Roshan City Building No-5 Wing GMahaRERA P99000021141

by Manibhadraa Parivar Infraprojects

Gat No 30/2 and 31, Palghar West, 401404

Dec 2026
Possession
70.5%
Built
0
Complaints
24
Units
High risk
  • Possession delayed ~4 yrs. Originally promised May 2023, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P99000021141
Status
New
Stage
Certificate Signed
Possession
December 2026originally May 2023
Construction
70.5% complete
Units sold
3 of 24

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2019
Floors
5
Unit mix
24 res ยท 0 comm
Architect
Vasturachna Consultants

Buyer community

Connect with other buyers and owners of Star Roshan City Building No-5 Wing G โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Star Roshan City Building No-5 Wing G. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.