Haware Nakshatra Phase 3MahaRERA P99000022307
661, Opp Dandekar College, 401404
Dec 2026
Possession
93.8%
Built
0
Complaints
116
Units
Caution
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P99000022307
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 93.8% complete
- Units sold
- 8 of 116
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Building & registration
- RERA registered
- Sept 2019
- Floors
- 8
- Unit mix
- 113 res ยท 3 comm
- Architect
- PB Associates
Buyer community
Connect with other buyers and owners of Haware Nakshatra Phase 3 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Haware Nakshatra Phase 3. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.