PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

VORA ASSOCIATES

by VORA ASSOCIATES

PLOT NO -2, S NO-10, H NO- 1 TO 7, SATIVALI VASAI EAST, 401208

Mar 2023
Possession
52.7%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 52.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2023 per the RERA filing.

Official RERA facts

Registration
P99000023417
Status
New
Stage
Certificate Signed
Possession
March 2023
Construction
52.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting30%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Dec 2019
Floors
3

Buyer community

Connect with other buyers and owners of VORA ASSOCIATES โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VORA ASSOCIATES. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.