ORCHID VILLASMahaRERA P99000024168

by SHARP DEVELOPERS

S NO 57, 58/1, 59/1, 60/1, CHINCHOTI, 401208

Dec 2030
Possession
89.1%
Built
2
Complaints
130
Units
High risk
  • Possession delayed ~4 yrs. Originally promised May 2027, now proposed Dec 2030 per the RERA filing.

Official RERA facts

Registration
P99000024168
Status
New
Stage
Certificate Signed
Possession
December 2030originally May 2027
Construction
89.1% complete
Units sold
84 of 130

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2020
Floors
23
Unit mix
130 res ยท 0 comm
Architect
MUFFADAL MERCHANT

Buyer community

Connect with other buyers and owners of ORCHID VILLAS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ORCHID VILLAS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.