Under construction
RAMESH HEIGHTS PHASE 1MahaRERA P99000026830
SURVEY NO.7 HISSA NO.1A,2A , SURVEY NO.8, NILEMORE, 401203
Dec 2026
Possession
71.4%
Built
0
Complaints
65
Units
Caution
- Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P99000026830
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally June 2024
- Construction
- 71.4% complete
- Units sold
- 57 of 65
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths95%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Landscaping & Tree Planting95%
Street Lightingnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Oct 2020
- Floors
- 9
- Unit mix
- 65 res ยท 0 comm
- Architect
- ABHAY RAUT
Buyer community
Connect with other buyers and owners of RAMESH HEIGHTS PHASE 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching RAMESH HEIGHTS PHASE 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.