PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAI VAIBHAVMahaRERA P99000027556

by A D Constructions

Survey No - 99/2/1/2 CTS No - 1455, Palghar West, 401404

May 2021
Possession
70.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (May 2021) has passed with construction at 70.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2021 per the RERA filing.

Official RERA facts

Registration
P99000027556
Status
New
Stage
Certificate Signed
Possession
May 2021
Construction
70.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2020
Floors
5

Buyer community

Connect with other buyers and owners of SAI VAIBHAV โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI VAIBHAV. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.