Under construction

GIRDHARI HEIGHTS

by SHREE KRISHNA DEVELOPERS

Survey No.30/1/1,30/1/3,329/B,329-1/C/2/1//2/2,329-1/C/3B,329/C of VILLAGE-VIRAR,TALUKA-VASAI,DIST.PALGHAR ,BLDG NO.5, Vasai, 401305

High risk
  • Possession delayed ~1 yr. Originally promised Dec 2024, now proposed Apr 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 80.5%.

Official RERA facts

Registration
P99000029298
Status
New
Stage
Certificate Signed
Possession
April 2026originally December 2024
Construction
80.5% complete
Units sold
44 of 67

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
May 2021
Floors
9
Unit mix
67 res ยท 0 comm
Architect
AJAY WADE & ASSOCIATES

Buyer community

Connect with other buyers and owners of GIRDHARI HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GIRDHARI HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.