NIRVANA ECO HOMES BLDG NO 03MahaRERA P99000030880

by ASIATIC STRUCTURES LLP

268, ALYALEE, 401404

Dec 2027
Possession
59.5%
Built
0
Complaints
94
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000030880
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
59.5% complete
Units sold
1 of 94

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2021
Floors
8
Unit mix
94 res ยท 0 comm
Architect
A P ASSOCIATES

Buyer community

Connect with other buyers and owners of NIRVANA ECO HOMES BLDG NO 03 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIRVANA ECO HOMES BLDG NO 03. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.