Under construction

PARK - 16

by Fine Homes

Gut No - 182/8 Plot No -16, Palghar, 401102

Mar 2027
Possession
49.1%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Mar 2027 but construction is only at 49.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P99000034593
Status
New
Stage
Certificate Signed
Possession
March 2027
Construction
49.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2022
Floors
6

Buyer community

Connect with other buyers and owners of PARK - 16 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PARK - 16. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.