PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

IMPERIALPARAMOUNTMahaRERA P99000046574

by Shivganga Construction & Redevelopers

S.NO-34H.NO- 1 & 4, NALLASOPARA WEST, 401209

Dec 2026
Possession
64.5%
Built
0
Complaints
259
Units
High risk
  • Possession delayed ~1 yr. Originally promised Nov 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P99000046574
Status
New
Stage
Certificate Signed
Possession
December 2026originally November 2025
Construction
64.5% complete
Units sold
109 of 259

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2022
Floors
17
Unit mix
156 res ยท 103 comm

Buyer community

Connect with other buyers and owners of IMPERIALPARAMOUNT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching IMPERIALPARAMOUNT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.