ROYAL DREAMS PRIDEMahaRERA P99000048989

by ALBERT AUGSTIN RODRIGUES

S NO 150 HISSA NO 1/1 and 1/2, NALLASOPARA EAST, 401209

Dec 2027
Possession
49.1%
Built
0
Complaints
48
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2024, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000048989
Status
New
Stage
Certificate Signed
Possession
December 2027originally June 2024
Construction
49.1% complete
Units sold
14 of 48

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2023
Floors
8
Unit mix
35 res ยท 13 comm
Architect
SHAPE CONSULTANTS

Buyer community

Connect with other buyers and owners of ROYAL DREAMS PRIDE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ROYAL DREAMS PRIDE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.