Under construction

RUBY GOLDMahaRERA P99000052144

by SHAKEEL ABDULREHMAN MUNSHIRAZA KHAN

SURVEY NO.380 PLOT NO.60 AND PLOT NO.70, SURVEY NO 380 PLOT NO 60 AND PLOT NO 70 NEXT TO JP INTERNATIONAL SCHOOL, 401404

Mar 2027
Possession
78.6%
Built
0
Complaints
42
Units
Caution
  • Possession delayed ~1 yr. Originally promised Feb 2026, now proposed Mar 2027 per the RERA filing.

Official RERA facts

Registration
P99000052144
Status
New
Stage
Certificate Signed
Possession
March 2027originally February 2026
Construction
78.6% complete
Units sold
12 of 42

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvesting80%
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jul 2023
Floors
6
Unit mix
30 res ยท 12 comm
Architect
PRANAV DESHMUKH

Buyer community

Connect with other buyers and owners of RUBY GOLD โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RUBY GOLD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.