Under construction

SHREE SAI DARSHANMahaRERA P99000052942

by IMPERIAL INFRAREALTY PRIVATE LIMITED

SURVEY NO. 25/1/A, PLOT NO. 43, NAVALI, 401404

Jun 2027
Possession
74.5%
Built
0
Complaints
21
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P99000052942
Status
New
Stage
Certificate Signed
Possession
June 2027originally December 2025
Construction
74.5% complete
Units sold
15 of 21

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2023
Floors
8
Unit mix
21 res ยท 0 comm

Buyer community

Connect with other buyers and owners of SHREE SAI DARSHAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREE SAI DARSHAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.