Under construction

SHRIPAL SHANTI - T2MahaRERA P99000054078

by SHRIPAL SHANTI LLP

S. NO. 131 H. NO.2,S. NO. 132, S. NO. 133 H. NO. 2, BOLINJ, 401303

Dec 2030
Possession
31.5%
Built
0
Complaints
203
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Mar 2027, now proposed Dec 2030 per the RERA filing.

Official RERA facts

Registration
P99000054078
Status
New
Stage
Certificate Signed
Possession
December 2030originally March 2027
Construction
31.5% complete
Units sold
1 of 203

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Dec 2023
Floors
24
Unit mix
203 res ยท 0 comm
Architect
ENCON

Buyer community

Connect with other buyers and owners of SHRIPAL SHANTI - T2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHRIPAL SHANTI - T2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.