๐Ÿ—๏ธ
Under construction

FIA EKAANTMahaRERA P99000056217

by Fia Developers Pvt. Ltd.

SURVEY NO. - 826 , FINAL PLOT NO. 95, MAHIM, 401404

Feb 2026
Possession
81.8%
Built
0
Complaints
25
Units
Caution
  • Possession date passed. The proposed possession date (Feb 2026) has passed with construction at 81.8%.

Official RERA facts

Registration
P99000056217
Status
New
Stage
Certificate Signed
Possession
February 2026originally December 2025
Construction
81.8% complete
Units sold
23 of 25

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
May 2024
Floors
6
Unit mix
20 res ยท 5 comm
Architect
VASTU SHILP

Buyer community

Connect with other buyers and owners of FIA EKAANT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching FIA EKAANT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.