Under construction
GALAXY PRIDEMahaRERA P99000077904
S.NO. - 827/5/A ,827/6/A, FINAL PLOT NO.5,6, MAHIM, 401404
Jun 2027
Possession
39.5%
Built
0
Complaints
25
Units
High risk
- Behind schedule. Possession is due Jun 2027 but construction is only at 39.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P99000077904
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 39.5% complete
- Units sold
- 1 of 25
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Nov 2024
- Floors
- 6
- Unit mix
- 25 res ยท 0 comm
- Architect
- VASTU SHILP ASSOCIATES
Buyer community
Connect with other buyers and owners of GALAXY PRIDE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching GALAXY PRIDE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.