OCEAN PEARL
CTS NO 1056/5 PARDI NO 23 PO VILLAGE MALONDE, VILLAGE MALONDE, 401201
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Behind schedule. Possession is due Dec 2026 but construction is only at 2.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P99000079765
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 2.3% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Litigation record1 case
- HIGH COURT OF MUMBAICase 26134/2023PRE ADMISSION
Landowner
SAGAR DARSHAN CO-OPERATIVE HOUSING LIMITED
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2025
- Floors
- 8
- Plot / CTS / survey no.
- CTS NO 1056/5 PARDI NO 23 PO VILLAGE MALONDE
- Planning authority
- Others
- Approved layout land
- 456.5 sq.m
- Land for this registration
- 456.5 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 11,505.56 sq.m
- Registered office
- NA
- North
- North - Dreenal Apartments
- South
- West - Bandhan Housing society
- East
- East - Kutir Housing Society
- West
- South - Main RoadSouth - Main Road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- HDFC BANK โ 48862IFSC HDFC0000408MANGESH BHUVAN GURU NANAK NAGAR AMBADI ROAD VASAI WEST 401202
Commencement Certificate documents
- 7 Commencement Certificates.pdf
Buyer community
Connect with other buyers and owners of OCEAN PEARL โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching OCEAN PEARL. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.