Under construction

ORCHID

by ROYALE URBANSPACE LLP

206-216, SHAHAPUR, 421601

Jul 2019
Possession
90.9%
Built
2
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jul 2019) has passed with construction at 90.9%.

Official RERA facts

Registration
P51700011790
Status
Ongoing
Stage
Certificate Signed
Possession
July 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains70%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving station80%

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of ORCHID โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ORCHID. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.