All RERA projects
ROYALE URBANSPACE LLP
6 MahaRERA-tracked projects in Mumbai
6
Tracked projects
3
Complaint records
0
Recovery warrants
Computed only from official MahaRERA disclosures across this builder's (spelling-matched) portfolio.
Projects (6)
- 97 · A+FENNEL HSHAHAPURPossession Dec 202378.7% built
- 93 · A+ORCHIDSHAHAPURPossession Jul 201990.9% built2 complaints
- 92 · A+FENNEL DSHAHAPURPossession Dec 201973.5% built
- 92 · A+TULIP NSHAHAPURPossession Dec 201953.2% built
- 89 · AFENNEL GSHAHAPURPossession Dec 202661.8% built
- 83 · ATULIP PSHAHAPURPossession Dec 201945.5% built1 complaints
Data from official MahaRERA public disclosures; promoter spellings are grouped automatically (slug: royale-urbanspace). Scores are PropPin's transparent rule-based rating — every factor cites a disclosure. Not investment advice.