RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 1 of 61
- Bloomdale Building 10 B9.4 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500008833· filed Jan 2019 → now May 2017· 90.9% built
- RIDDHI SIDDHI PLAZA8.9 yr overdueGOPAL TRILOKCHAND AGRAWAL · CIDCO N-4, AurangabadP51500014798· 64.5% built
- GALAXY ONE8.9 yr overdueMODULAR CONSTRUCTIONS ·P52100012216· 86.8% built· 4 complaints
- Rite Prime8.9 yr overdueRite Developers Pvt. Ltd. · Andheri, Mumbai SuburbanP51800010472· 90.9% built
- GOVIND VILAS8.9 yr overdueM/S SWAMI OM PROPERTIES · Pune City, PuneP52100008590· 90.9% built
- Garva Residency-C38.9 yr overdueGarva Developers Pvt Ltd · Warse, RaigarhP52000006946· 70% built
- ROHAN ISHAN WING A 5 TO 11 FLOOR8.9 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Mulshi, PuneP52100000816· 90.9% built
- Grand Uno8.9 yr overdueGrandeur Infra · Kolhapur (M Corp.), KolhapurP53000004969· 90.9% built
- THE VRINDAVAN NAGAR CHS LTD8.9 yr overdueAMI HOUSING LIMITED · Kurla, Mumbai SuburbanP51800009398· 90.9% built
- Mangeshi Paradise - I8.9 yr overdueAnnapurna Universal · Kalyan-Dombivali (M Corp.), ThaneP51700010709· 86.4% built
- ORCHID8.9 yr overdueLOHIA DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000004970· 90.9% built
- Orchard8.9 yr overdueShiv Parvati Developers · Hadapsar, PuneP52100006525· 81.8% built
- GANADHISH8.9 yr overdueGANESH ENTERPRISES · anandvalli, NashikP51600004373· 90.9% built
- NAMDEO RUKARI BAUG8.9 yr overdueM/s. TULSI DEVELOPERS · Haveli, PuneP52100010486· 81.8% built
- WESTWINDS Wing D8.9 yr overdueShreeram Sankalp Associates · Pune City, PuneP52100004203· 97.7% built
- ARUNAREN RESIDENCY8.9 yr overdueSHILPIPROPERTY DEVELOPERS(BOMBAY) PVT LTD ·P52100010160· 90.9% built
- KAKADE RESIDENCY8.9 yr overdueBMK PROPERTIES PRIVATE LIMITED · Talegaon Dabhade (M Cl), PuneP52100004336· 81.8% built
- Construction of 14 Rowhouses at Waddhamna Nagpur8.9 yr overdueMHADA(Nagpur Board) · Waddhamna, NagpurP50500012638· 75.2% built
- SIDHESHWAR COMPLEX BUILDING 1 A WING8.9 yr overdueADESHWAR ASSOCIATES · TITWALA, ThaneP51700011114· 90.9% built
- SHIV SHANKAR RESIDENCY8.9 yr overdueSAI GURUKRUPA CONSTRUCTION & DEVELOPERS · Thane, ThaneP51700005594· 81.8% built
- OM DATTAPRASAD CO OP HSG SOCIETY LTD8.9 yr overdueKIRAN NARAYAN MANORE · Panvel, RaigarhP52000003980· 94.1% built
- Dhanwantari Terrace Cooperative Housing Society Limited8.9 yr overdueDigamber Parulekar · Kothrud, PuneP52100005496· 81.8% built
- SAI PEARL8.9 yr overdueSHREE DEVELOPERS · Karanjade, RaigarhP52000003239· 99.1% built
- Le Regalia Phase I BLDG C AND D8.9 yr overdueM/s. ShreePrakash Creative Buildcon J.V. · Nashik (M Corp.), NashikP51600009453· 90.9% built
- Sadguru Apartment8.9 yr overdueV R Construction · Nashik (M Corp.), NashikP51600008773· 90.9% built
- SAI MAJESTIC8.9 yr overdueS S DEVELOPERS · Wakad, PuneP52100002487· 55% built
- JP ENIGMA8.9 yr overdueJaiprakash Gurdasmal Khushalani · Nagpur (M Corp.), NagpurP50500013221· 90.9% built
- SADHGURU8.9 yr overdueSHREEDEV ENTERPRISE · Ulawe, RaigarhP52000007337· 90.9% built
- IMAGE8.9 yr overdueIMAGE A AUTHENTICITY OF DREAM · Ulawe, RaigarhP52000009300· 45.5% built
- MAYUR GEMINUS - B8.9 yr overdueBUNTY PROPERTIES UNIT NO. XI · Hadapsar, PuneP52100003518· 90.9% built
- RADHIKA PARK I8.9 yr overdueRADHIKA CONSTRUCTIONS ·P52100011202· 80.9% built
- SHANTI SADAN8.9 yr overdueMAN GLOBAL LTD. · Andheri, Mumbai SuburbanP51800008793· 90.9% built· 7 complaints
- Kiran Sanklp8.9 yr overdueM/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE · Sus, PuneP52100011477· 90.9% built
- Relax Homes8.9 yr overdueMohd Sajid Abdul Salam Pasha · Ibhadpada, PalgharP99000007696· 75.9% built
- DEVIPRABHA GAURAV8.9 yr overdueDEVIPRABHA BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500002678· 74.5% built
- Samarth Raghukul8.9 yr overdueM/S VIRTUE ENTERPRISES · Ward GNorth, Mumbai CityP51900007414· 71.8% built
- S. S. ICON - PHASE I8.9 yr overdueS S INFRASTRUCTURE · Near Rangraj Nagar, SolapurP52600013838· 81.8% built
- Ozone Residency B wing8.9 yr overdueWestcoastrealty · Alibag, RaigarhP52000007382· 90.9% built
- SAMYAKTH BLISS BUILDING 28.9 yr overdueSamyakth Realties · Andheri, Mumbai SuburbanP51800013227· 90.9% built
- VINAYAK HEIGHTS8.9 yr overdueR R BUILDERS & DEVELOPERS · Talegaon Dabhade (R), PuneP52100010646· 90.9% built
- MARUTI ASTHA8.9 yr overdueMARUTI HOMES · Badlapur (M Cl), ThaneP51700013850· 79.1% built
- RENUKA COTTAGE8.9 yr overdueCHETAN HIRALAL SHARMA · Satara (CT), AurangabadP51500013490· 40% built
- Anika Enclave8.9 yr overdueArun Pitamber Sheth · Pune City, PuneP52100001676· 90.9% built
- Y. K. NAGAR NX8.9 yr overdueSHREE ASHTAVINAYAK BUILDERS · Vasai-Virar City (M Corp), PalgharP99000010747· 90% built
- Mahavir Aria8.9 yr overdueMilestone Developers · Kurla, Mumbai SuburbanP51800000409· 72.7% built
- SKYLINE HEIGHTS8.9 yr overduePEARL PROPERTIES · Karanjade, RaigarhP52000008413· 90.9% built
- STAR BUILDERS AND DEVELOPERS8.9 yr overdueSTAR BUILDERS & DEVELOPERS · Vasai, PalgharP99000005302· 90.9% built
- MALPANI SAFFRON BUILDING NO 28.9 yr overdueGIRIRAJ ENTERPRISES · Nashik (M Corp.), NashikP51600008125· 72.7% built· 3 complaints
- Western India Mill8.9 yr overdueMHADA · Ward FSouth, Mumbai CityP51900000025· 90.9% built
- TROPICA PHASE I8.9 yr overdueOm Developers Project Ravet · Pimpri Chinchawad (M Corp.), PuneP52100003765· 90% built
- SHREE RAM KALPANA8.9 yr overdueNEELKANTH ASSOCIATES · Panvel, RaigarhP52000013551· 90.9% built
- SAI PUSHKRAJ8.9 yr overdueSAI ENTERPRISES · kondhwa BK, PuneP52100013136· 90.9% built
- SHANTINATH PLAZA8.9 yr overdueMAHENDRA MADANLAL GUNDECHA · Ratnagiri (M Cl), RatnagiriP52800006572· 72.7% built
- WHISPERING WINDS PHASE I8.9 yr overdueVYAS REALTIES PVT. LTD. · Pune (M Corp.), PuneP52100006242· 90.9% built
- VIGHNAHAR RESIDENCY8.9 yr overdueNAFIAH DEVELOPERS · Karanjade, RaigarhP52000004761· 90% built· 2 complaints
- Cosmopolis Phase 18.9 yr overdueCosmos Homes India Pvt. Ltd. · Andheri, Mumbai SuburbanP51800012114· 72.7% built· 5 complaints
- VARAD VASTU8.9 yr overdueSHARAD KHARADE · Hinjavadi (CT), PuneP52100013534· 81.8% built
- SUDAMA GREENS8.9 yr overdueSACHIN SUDAM PATIL · Thane, ThaneP51700010295· 90.9% built
- Gurukripa Appartment8.9 yr overdueROYAL DEVELOPERS · Nashik (M Corp.), NashikP51600011997· 81.8% built
- JANAVI PLAZA, JANAVI TOWER8.9 yr overdueJANAVI BUILDERS & DEVELOPERS · WALIV, PalgharP99000012849· 88% built
- MANAS ARADHANA APARTMENT8.9 yr overdueManas Developers · Jalgaon (M Corp.), JalgaonP49900002506· 90.9% built
- SAI GABHASTI8.9 yr overdueAndheri, Mumbai SuburbanP51800005461· 80% built
- Bhoomi Vijay Apartment8.9 yr overdueNarayan Jankiram Deshpande · Nashik, NashikP51600012879· 74.5% built
- INDRALOK HEIGHTS8.9 yr overdueINDRALOK CONSTRUCTION CO · Thane, ThaneP51700005737· 72.7% built
- Vighnarajendra8.9 yr overduePSC PROPERTIES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000476· 90.9% built
- Seawood Harmony8.9 yr overdueGeo Builders · Thane, ThaneP51700005814· 90.9% built
- ROHINI RESIDENCY OF JEEVAN KUNJ CHS LTD8.9 yr overdueAARYAN REALTORS · Kurla, Mumbai SuburbanP51800012290· 90.9% built
- SHANTI NIKETAN8.9 yr overdueSHREE SAIDATT DEVELOPERS · Karanjade, RaigarhP52000012693· 90.9% built
- MODI HOUSE8.9 yr overdueMODI ENTERPRISE · Borivali, Mumbai SuburbanP51800000872· 90.9% built
- PADMA CHS LTD8.9 yr overdueG.M.DEVELOPERS · Andheri, Mumbai SuburbanP51800002441· 90.9% built
- SPENTA8.9 yr overdueSVK PROJECTS LLP · Andheri, Mumbai SuburbanP51800000892· 90.9% built
- Arihant Avenue8.9 yr overdueDharmesh Vasantrai Shah · Haveli, PuneP52100009141· 81.4% built
- SHANTI KUNJ8.9 yr overdueSHREYAS ENTERPRISES · Thane, ThaneP51700004964· 53.9% built
- Arham Brindavan8.9 yr overdueMahavir Enterprises · Kurla, Mumbai SuburbanP51800004177· 90.9% built
- DATTUSAI COMPLEX BUILDING NO 28.9 yr overdueSAIRAJ ENTERPRISES · DOMBIVLI, ThaneP51700013185· 90% built
- Business Park8.9 yr overdueRoongta Buildcon Ltd. · Nashik, NashikP51600006641· 60.7% built
- JADE RESIDENCES - 28.9 yr overdueCREATOZ BUILDERS PRIVATE LIMITED · WAGHOLI, PuneP52100005242· 86.4% built· 18 complaints
- SHANTA NIVAS8.9 yr overdueSUNRISE DEVELOPERS · Mumbai City, Mumbai CityP51900010283· 72.3% built
- OM PARADISE B AND C WING8.9 yr overdueS K BUILDCON · KIWALE, PuneP52100002744· 72.7% built
- SHREE MANGAL8.9 yr overdueMANGAL BUILDHOME PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800004380· 90.9% built
- BHAGIRATHI VAIBHAV8.9 yr overdueM/S VAIBHAV DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500010547· 75.5% built
- SHARVARI WINDGATES, PHASE-I8.9 yr overdueADINATH DEVELOPERS · Punawale, PuneP52100006771· 72.7% built
- KANAK HEIGHT8.9 yr overdueSHANTILAL MISHRIMAL CHANDAN · Ward ABCD, Mumbai CityP51900012370· 80% built
- LODHA BELMONDO AUGUSTA C8.9 yr overdueLodha Developers Limited · Gahunje, PuneP52100000174· 90.9% built· 3 complaints
- SIDDHIVINAYAK JEWEL8.9 yr overdueSHRIKANT DHONDU HINDALKAR · Panvel, RaigarhP52000007395· 87.1% built
- REDEVELOPMENT OF KRIPADHAM CHS LTD8.9 yr overdueKRIPA REALTORS · Borivali, Mumbai SuburbanP51800013163· 90.9% built
- KULSWAMINI HEIGHTS8.9 yr overdueHARI OM DEVELOPERS · Kalyan, ThaneP51700005364· 89.4% built
- VRUNDAVAN - A WING8.9 yr overdueSHRI LAXMI BALAJI DEVELOPERS · charholi kh, PuneP52100011028· 90.9% built
- Maniganesh Tower8.9 yr overdueKishorkumar Bajranglalji Chokhani · Yavatmal (M Cl), YavatmalP51000008147· 90.9% built
- SAI DEVELPOER8.9 yr overdueSAI DEVELOPERS · Wadagaon (CT), PuneP52100005487· 90.9% built
- NEW SKY STAR DEVELOPERS8.9 yr overdueNew Sky Star Developers · Vasai-Virar City (M Corp), PalgharP99000012093· 90.9% built
- GOLDEN BELLS PHASE I8.9 yr overduePIONEER CONSTRUCTIONS · Haveli, PuneP52100004990· 90.9% built
- Tara Jewel8.9 yr overdueTara Jewel · Haveli, PuneP52100007418· 72.7% built
- MAJITHIA SWASTIK GALAXY8.9 yr overdueSWASTIK ASSOCIATES · Vasai, PalgharP99000013190· 89.1% built
- POONAM PALASH8.9 yr overdueSUMIT JAWAHARLAL JAIN · Vasai, PalgharP99000013226· 81.5% built· 1 complaint
- GUNDECHA TRILLIUM8.9 yr overdueSEA PRINCESS REALTY · Borivali, Mumbai SuburbanP51800001115· 97% built· 16 complaints
- SHUBHAM RESIDENCY8.9 yr overduePOTE SONS BUILDERS & DEVELOPERS · Karanjade, RaigarhP52000006093· 90.9% built
- Krushnasundar Residency8.9 yr overdueSanjay Baliram Jadhav · Aurangabad (M Corp.), AurangabadP51500010862· 90.9% built
- AAKASHA CHSL8.9 yr overdueTrivenidevelopers · Borivali, Mumbai SuburbanP51800007596· 78.6% built
- IPSIT NAVODAY PHASE 18.9 yr overdueIPSIT ENTERPRISE · Palghar, PalgharP99000002933· 65.5% built· 1 complaint
- VIVA VEDANTA - BLDG NO. 28.9 yr overdueVIVA HOMES PRIVATE LIMITED · Vasai, PalgharP99000007076· 90.9% built
- LAXMI NARAYAN8.9 yr overdueSIDDHIVINAYAK DEVELOPERS ·P52100006320· 90.9% built
- K City Centre8.9 yr overdueKharde Patil Enterprises · Kopargaon (M Cl), AhmednagarP52200013594· 80% built
- TARGET THE MALL8.9 yr overdueMAHENDRA JAMNADAS KARA · Borivali, Mumbai SuburbanP51800006542· 77.3% built· 2 complaints
- LODHA BELMONDO ASHBRIDGE D, E8.9 yr overdueLodha Developers Limited · Gahunje, PuneP52100011522· 90.9% built· 2 complaints
- VARDHAMAN PARK8.9 yr overdueCHRISHH OMKARA CONSTRUCTIONS · Varale, PuneP52100008190· 90.9% built
- Tulsai Heights8.9 yr overdueSachin Kishanrao Padwal · Bhosari, PuneP52100002513· 90.9% built
- INDRAYAN8.9 yr overdueGruha Navnirman Developers · Pune (M Corp.), PuneP52100001253· 81.8% built
- HARMONY8.9 yr overdueUTTAM ASSOCIATE · Talegaon Dabhade (M Cl), PuneP52100012594· 90.9% built
- CORE8.9 yr overdueAHURA BUILDERS · Pune (M Corp.), PuneP52100013229· 90.9% built
- SOLITAIRE8.9 yr overdueVENUS SASCON DEVELOPERS · Pune (M Corp.), PuneP52100003846· 72.7% built
- BHUVI8.9 yr overdueM/s Vitthal Properties · Wakad, PuneP52100008707· 81.8% built
- Kush Prestige8.9 yr overdueKush Buildcon LLP · Andheri, Mumbai SuburbanP51800002724· 90.9% built
- Madhumalti8.9 yr overdueDilip Madhukar Dalvi · Kalyan-Dombivali (M Corp.), ThaneP51700012542· 90.9% built· 4 complaints
- ASHLESHA8.9 yr overdueSHARAD MAHADEO SARAVADE · Panvel, RaigarhP52000014125· 78.2% built
- PLATINUM LIVIANO8.9 yr overduePLATINUM LIFESTYLE LLP · Panvel, RaigarhP52000005906· 90.9% built
- Gangwani Plaza8.9 yr overdueGangwani Constructions Pvt LtdAA · Nagpur (M Corp.), NagpurP50500011201· 85.9% built
- Priya Girish Vihar CHS Ltd8.9 yr overdueAmeya Developers · Kurla, Mumbai SuburbanP51800006961· 90.9% built
- SHREE NARAYANA CLASSIC8.9 yr overdueSHREE LAXMI VENTURE PVT LTD · Umred (M Cl), NagpurP50500000583· 90.9% built
- Soham8.9 yr overdueS B Constructions · Nashik (M Corp.), NashikP51600013041· 81.8% built
- Ikebana8.9 yr overdueM/s. Tejukaya Realty · Mumbai City, Mumbai CityP51900012152· 97.7% built
- Swapneel Phase 28.9 yr overdueM/S Waman Constructions · Pimpri Chinchawad (M Corp.), PuneP52100003744· 90.9% built
- RAJ HILLS PHASE II8.9 yr overdueSACHIN YAGNESHWAR PATIL · Vasai, PalgharP99000005109· 86.8% built
- SHAGUN APARTMENT8.9 yr overdueSHREE VARAD VINAYAK DEVELOPERS · Taloje Panchnad, RaigarhP52000013848· 66.4% built
- Welkin Star8.9 yr overdueWELKIN DEVELOPERS · ULAWE, RaigarhP52000011234· 90.9% built
- PAREES HEIGHTS8.9 yr overdueANIL SUBHAN PATIL · Jalgaon (M Corp.), JalgaonP49900011012· 90.9% built
- Mittal Aristo8.9 yr overdueAditdev Builders LLP · Ward FSouth, Mumbai CityP51900007964· 90.7% built
- SOHAM SUMY MADHURYA8.9 yr overdueSOHAM SUMY DEVELOPERS LLP · Wakad, PuneP52100009818· 64.5% built
- Om Sai Residency8.9 yr overdueOm Sai Residency · Manda, ThaneP51700013426· 90.9% built
- LODHA FRESHIA WING A, B, C8.9 yr overdueLodha Developers Limited · Kalyan, ThaneP51700004667· 90.9% built
- Pyramid city 18.9 yr overduePyramid Arcades Pvt Ltd · Nagpur (M Corp.), NagpurP50500012106· 90.9% built
- Sharvari Primero8.9 yr overdueSHARVARI REALTORS LLP · Kalyan, ThaneP51700000601· 9.8% built
- R N AVENUE8.9 yr overdueR N BUILDERS · Karanjade, RaigarhP52000003363· 90.9% built
- Nirman8.9 yr overdueJPV Realtors Private Limited · Borivali, Mumbai SuburbanP51800003080· 90.9% built
- SAI ASHISH II8.9 yr overdueKUKREJA CONSTRUCTION CO · Kurla, Mumbai SuburbanP51800009725· 72.7% built
- Earth Classic8.9 yr overdueEarthClassic · Mumbai City, Mumbai CityP51900005225· 90.9% built
- SIDDHI BELEZZA8.9 yr overdueSIDDHITAPASWI BUILDTECH · Panvel, RaigarhP52000010558· 90.9% built
- RAJVEER HEIGHTS C WING8.9 yr overdueSHRI DATTASAI DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000013241· 81.8% built
- Lotus Prestige8.9 yr overdueEssen Builders and Developers · Borivali, Mumbai SuburbanP51800011399· 90.9% built
- GOKULDHAM APPARTMENT8.9 yr overdueSHREE BALAJI BUILDERS AND DEVELOPERS · NASHIK, NashikP51600009696· 90.9% built
- PUSHKARAJ8.9 yr overdueINOVIIC DEVELOPER · Kothrud, PuneP52100008994· 90.9% built· 1 complaint
- Suguru Datta - C Building8.9 yr overdueSuguru Realty LLP · Pashan, PuneP52100006537· 81.8% built
- KRISHNAI8.9 yr overdueLOHIA DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000013184· 90.9% built
- Tulsi Sapphire8.9 yr overdueSHREE MAHAVIR DEVELOPERS · Ulawe, RaigarhP52000001395· 90.9% built
- SBM MYRA8.9 yr overdueSBM PROPERTIES ·P52100004121· 90.9% built
- Maple Woodz phase-28.9 yr overdueWindsor Shelters · Taware Colony, PuneP52100009772· 90.9% built
- HARI ANAND8.9 yr overdueDHARAN INFRA-EPC LIMITED · Nashik, NashikP51600001348· 90.9% built
- Construction of Building No 32.Shopping Center at Bimbisar nagar ,W. E. Highway,Goregaon East8.9 yr overdueMUMBAI HOUSING AND AREA DEVELOPMENT BOARD · Borivali, Mumbai SuburbanP51800000057· 54.8% built
- BHALCHANDRA8.9 yr overdueKALYANI VILAS · Pune City, PuneP52100012906· 72.7% built
- Mukti Nakshtra E and H bldg8.9 yr overdueMukti Township Development & Construction Co. Pvt. Ltd. · Baramati (M Cl), PuneP52100002811· 81.8% built
- Construcion of 28 LIG tenement on Plot OB 8,Siddharth nagar ,Goregaon west,Mumbai8.9 yr overdueMUMBAI HOUSING AND AREA DEVELOPMENT BOARD · Borivali, Mumbai SuburbanP51800000031· 90.9% built· 2 complaints
- MANGALMURTI RESIDENCY8.9 yr overdueJAGDAMBA DEVELOPERS · Tisgaon, AurangabadP51500002019· 63.6% built
- AMOGH8.9 yr overdueBhalchandra Vinayak Wadnerkar · Mumbai City, Mumbai CityP51900002599· 90.9% built
- SAI ARCADE8.9 yr overdueSAI DEVELOPERS · Badlapur (M Cl), ThaneP51700009522· 90.9% built
- Modispaces Oyster8.9 yr overdueModispaces Real Estate Pvt Ltd · Borivali, Mumbai SuburbanP51800008356· 90.9% built
- SAI POOJA8.9 yr overduePARAS BHOMRAJ OSWAL · Kolhapur (M Corp.), KolhapurP53000010700· 87.3% built
- GEETANJALI8.9 yr overdueKUKREJA CONSTRUCTION CO · Kurla, Mumbai SuburbanP51800000280· 72.7% built
- KARMAA GALAXY8.9 yr overdueKARMAA REALTY · Nashik (M Corp.), NashikP51600003024· 60% built
- SAWLARAM SRUSHTI8.9 yr overdueSHREE SAI BUILDERS AND DEVELOPERS · Kalyan, ThaneP51700002398· 73.1% built
- AMBAR DARSHAN8.9 yr overdueSHIVSHAKTI BUILDERS & DEVELOPERS · Haveli, PuneP52100008843· 86.4% built
- KANJI TOWER8.9 yr overdueVIJAYABEN KANJI ASHRA · Mumbai City, Mumbai CityP51900008342· 90.5% built
- VENKATESHWARA8.9 yr overdueSHREE HARI PROJECTS · Phaltan (M Cl), SataraP52700006019· 63.6% built
- Nav Nirmal8.9 yr overdueDigamber Parulekar · Kothrud, PuneP52100003211· 81.8% built
- KRISHNA NIWAS8.9 yr overdueSHREE KRISHNA HOMES PVT LTD · Kurla, Mumbai SuburbanP51800008073· 90.9% built
- CITY RESIDENCY8.9 yr overdueSALEEM ADAM KASKAR · Chiplun (M Cl), RatnagiriP52800014177· 31.8% built· 2 complaints
- VIVA AAKANKSHA COMPLEX PHASE 18.9 yr overdueVIVA AAKANKSHA BUILDERS & DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000007383· 77.5% built
- Shubham Siddhi8.9 yr overdueShubham Realtors · Wadagaon (CT), PuneP52100008013· 81.8% built
- BHONGADE PARK III8.9 yr overdueSHARAD BABANRAO BHONGADE · Varale, PuneP52100003152· 99.1% built
- Prachi Residency Phase II8.9 yr overdueSancheti Associates · Baner, PuneP52100003737· 90.9% built
- BANKERS TOWER CO OP HSG SO8.9 yr overdueBANKERS TOWER CHS · Bamandongri, RaigarhP52000010516· 70% built
- SAi JHAROKHA8.9 yr overdueSwastik Space · Borivali, Mumbai SuburbanP51800001686· filed Sept 2017 → now Dec 2017· 90.9% built
- GURUMAULI COMPLEX8.9 yr overdueSahyadri Constructions and Developer Company · Haveli, PuneP52100014282· 84.5% built· 3 complaints
- Tara Ashirvaad8.9 yr overdueShivtara Properties Private Limited · WAGHOLI, PuneP52100008560· 72.7% built
- USHA KIRAN RESIDENCY WING E1 E2 E38.9 yr overdueSTALWART IMPEX PVT LTD · Badlapur (M Cl), ThaneP51700012135· 84.8% built
- Nikunj Navyangan8.9 yr overdueCALYX MERLIN VENTURES LLP · Mulshi, PuneP52100000512· 87.9% built
- ATUR VALLY VISTA WING B8.9 yr overdueATUR INDIA PRIVATE LIMITED · Pisoli, PuneP52100003801· 95% built
- PARIJAT BUILDING A8.9 yr overdueSHRI VENKATESH SHARADA INFRACON · AMBEGAON, PuneP52100005323· 81.8% built· 4 complaints
- RASIKA BUILDERS AND DEVELOPERS NERAL8.9 yr overdueRAVINDRA RAMCHANDRA BHOIR · Mamdapur, RaigarhP52000005131· 90.9% built
- Green Leaf8.9 yr overdueVIKRANT VIJAYRAO BHUTE · AALODI, WardhaP50400012613· 77% built
- Audumbar8.9 yr overdueMawlankar Lagad Associates · Baner, PuneP52100004181· 81.8% built
- MAHAVIR VILLA8.9 yr overdueVIPUL BHIMSHI SATRA · Panvel, RaigarhP52000004151· 87.3% built
- BELLAGIO8.9 yr overdueSRUSHTI DEVELOPERS · Haveli, PuneP52100004894· 90.9% built
- Mahaveer Delight8.9 yr overdueYashodhan Associates · Pune (M Corp.), PuneP52100007439· 84.5% built· 38 complaints
- HIRAMANDA HEIGHTS8.9 yr overdueHIRAMANDA DEVELOPERS · Shirur, PuneP52100004488· 90.9% built
- Nirman Ajinkyatara Wing D8.9 yr overdueNIRMAN DEVELOPERS · Pune (M Corp.), PuneP52100004880· 81.8% built
- JUNCTION 4068.9 yr overdueMISHAL REALTY · Panvel, RaigarhP52000011771· 81.8% built
- Gulmohar celebration8.9 yr overdueCREATIONPROPERTIES · Sangli Miraj Kupwad (M Corp.), SangliP53100012637· 81.8% built
- BRIZO RESIDENCY8.9 yr overdueFATCAT INFRASTRCTURE PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800008276· 90.9% built· 1 complaint
- CHOWHAN RESIDENCY/ AMALTAS8.9 yr overdueThe Lifestile Realty · UNDRI, PuneP52100004955· 66.8% built
- Sai Sawali A8.9 yr overdueP V REALTY · Vasai, PalgharP99000004922· 90.9% built
- KANHA RESIDENCY8.9 yr overdueKANHA MOTIRAM KENE · Kalyan, ThaneP51700006676· 90% built
- REDEVELOPMENT OF THE STATE BANK OF INDIA SIDDHESHWAR CO OP HOUSING SOC LTD8.9 yr overdueORRA REALTORS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800010846· 80.9% built
- vedant nakshatra ABC phase 18.9 yr overdueMOHAN HARDASMAL THARWANI · Badlapur (M Cl), ThaneP51700013039· 90.9% built
- New Shiv Shubham8.9 yr overdueWaghandCompany · Nashik Road, NashikP51600013437· 90.9% built
- SAPPHIRE BLISS8.9 yr overdueRAJESH BIJLANI · Panvel, RaigarhP52000009941· 72.7% built
- TEJAL APARTMENT8.9 yr overdueSAIRAM TRADERS · Vasai, PalgharP99000013936· 81.8% built
- SHREE TULSI KUNJ8.9 yr overdueSHREE ENTERPRISES · DINDORI ROAD, NashikP51600012894· 90.9% built
- Swami Krupa8.9 yr overdueMeenal Prakash Rao · Wadagaon (CT), PuneP52100012744· 81.8% built
- Ashish8.9 yr overdueDamle Tapdia Developer · Pune (M Corp.), PuneP52100009633· 81.8% built
- Rite Celesta8.9 yr overdueRite Developers Pvt. Ltd. · Borivali, Mumbai SuburbanP51800004974· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.