PropPin
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
SWAYAMBHU SIDDHI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
AMBER SHINDE

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P53100048449
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
80.9% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.