PropPin
High risk
  • Mortgaged to a lender (₹2 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹2 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
AVANEESH BUILDCON LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
AMBER SHINDE

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P53100049307
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
60% complete
Units sold
2 of 34

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.