Under construction
K-SQUARE APARTMENTS
MahaRERA P50500003259High risk
KH NO 65/3 CTS NO 512 512/2, Nagpur (M Corp.), 440015
Post your property hereOwn or renting out a unit in K-SQUARE APARTMENTS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Nagpur (M Corp.) come to you.
Mar 2019
Possession
90.9%
Built
36
Complaints
0
Units
High risk
- 36 RERA complaints. 36 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 90.9%.
Area guide
What it's like to buy in Nagpur (M Corp.)
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
ANKIT CONSTRUCTION
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P50500003259
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Nagpur (M Corp.)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SHRIKRUSHNA BUILDERS AND DEVELOPERS
Nagpur (M Corp.)Poss. July 2019
PIONEER ORION
Nagpur (M Corp.)Poss. December 2018
GOVIND RESIDENCY-II
Nagpur (M Corp.)Poss. December 2027
Metrocity - 11
Nagpur (M Corp.)Poss. December 2030
SHANTAI
Nagpur (M Corp.)Poss. July 2032
MADHAV NAGARI
Nagpur (M Corp.)Poss. September 2018
ROYAL HEIGHTS
Nagpur (M Corp.)100% builtPoss. January 2018
Ivory Palms
Nagpur (M Corp.)100% builtPoss. December 2017
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.