PropPin
High risk
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 21.2%.

Promoter

Builder profile

Builder
S P ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P50500009890
Status
Ongoing
Stage
Certificate Signed
Possession
June 2018
Construction
21.2% complete
Units sold
0 of 0

Similar projects in Nagpur (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.