PropPin
Caution
  • Possession date passed. The proposed possession date (May 2019) has passed with construction at 72.3%.

Promoter

Builder profile

Builder
SBM DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P50500015456
Status
New
Stage
Certificate Signed
Possession
May 2019
Construction
72.3% complete
Units sold
0 of 0