High risk
  • Possession date passed. The proposed possession date (Feb 2023) has passed with construction at 52.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2023 per the RERA filing.

Promoter

Builder profile

Builder
ANNAPURNA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P50500015526
Status
New
Stage
Certificate Signed
Possession
February 2023originally February 2022
Construction
52.3% complete
Units sold
0 of 0