PropPin
High risk
  • Possession delayed ~1 yr. Originally promised Jun 2024, now proposed Jul 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2025) has passed with construction at 86.4%.

Promoter

Builder profile

Builder
Shri Swami Samarth Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P50500025822
Status
New
Stage
Certificate Signed
Possession
July 2025originally June 2024
Construction
86.4% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.