Jul 2025
Possession
86.4%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised Jun 2024, now proposed Jul 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Jul 2025) has passed with construction at 86.4%.
Promoter
Builder profile
Shri Swami Samarth Developers
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P50500025822
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2025originally June 2024
- Construction
- 86.4% complete
- Units sold